Tee Ltd has contracted to use Vee Ltd’s “Grand Hotel” for a business conference. Which of the following would be regarded as a valid reason for Vee Ltd for the unavailability of the hotel on the agreed date under the law of frustration?
- i. The hotel was closed due to flood damage.
- ii. The hotel was double booked.
- iii. The hotel manager had arranged to have the hotel redecorated. The decorators had failed to complete the work by the agreed date.
B. iii only.
C. ii and iii only.
D. i, ii and iii.
Answer: A